Microsoft 74-343 Exam Syllabus Topics:

SectionWeightObjectives
Communicate Project Information10%- Share project data
  • 1. Use collaboration features
    • 2. Export and print project information
      - Customize views and reports
      • 1. Modify existing views and tables
        • 2. Generate and format standard reports
          Track and Analyze a Project20%- Analyze project performance
          • 1. Adjust schedules to meet targets
            • 2. Use tracking views and reports
              • 3. View variance and progress indicators
                - Set and update baselines
                • 1. Create and save baselines
                  • 2. Record actual progress and values
                    Create a Task-Based Schedule25%- Enter and organize tasks
                    • 1. Create task hierarchies and WBS
                      • 2. Set milestones and deadlines
                        • 3. Define task types and durations
                          - Establish task relationships
                          • 1. Define dependencies and constraints
                            • 2. Adjust critical path
                              • 3. Apply lead and lag time
                                Manage Resources and Assignments25%- Assign and manage resources
                                • 1. Assign resources to tasks
                                  • 2. Adjust assignment units and work values
                                    • 3. Resolve resource overallocation
                                      - Create and configure resources
                                      • 1. Define work, material, and cost resources
                                        • 2. Set resource calendars and costs
                                          Initialize a Project20%- Customize project settings
                                          • 1. Create custom fields and tables
                                            • 2. Modify display options
                                              • 3. Set scheduling options
                                                - Create a new project
                                                • 1. Set project start/finish dates
                                                  • 2. Configure calendars and working time
                                                    • 3. Define project properties

                                                      74-343 Exam FAQs: Honest Answers

                                                      Yes — the vendor's recommended training:

                                                      Training classes demand schedules; practice questions demand only spare minutes. After any course, the 74-343 questions from DumpsActual measure how much of it will survive exam day.

                                                      The Microsoft Managing Projects with Microsoft Project 2013 blueprint has 5 domains, led by Manage Resources and Assignments (25%), Create a Task-Based Schedule (25%), Initialize a Project (20%). Think of the weightings as the vendor's hint about where points concentrate — plan your hours accordingly. The complete outline above lists every subtopic.

                                                      Registration happens through the vendor's official channels:

                                                      The exam is delivered Retired as of July 31, 2019; previously available via Pearson VUE (online proctored or onsite testing center) — choose the arrangement that works for you when you book.

                                                      Passing the 74-343 exam earns you the Microsoft Specialist certification at the Specialist level — Microsoft's official verification of your skills. It's considered important because it's genuinely difficult, which is exactly why it carries weight with employers.

                                                      40-60 questions in 90-120. That combination rewards candidates who've trained their pace, not just their memory — so before the real thing, run full timed sessions in the DumpsActual engine, practice flagging hard questions instead of fighting them, and learn what your sustainable per-question rhythm feels like.

                                                      Delivery is instant: successful payment triggers an automatic email with your product, arriving in about a minute — install on unlimited computers, and if 2 hours pass with nothing, our 24/7/365 customer service will fix it fast. The guarantee: take the corresponding 74-343 exam within 60 days of purchase, and if you fail, submit a scanned enrollment slip plus the official Score Report PDF within 2 days of the exam for a 100% refund processed within 7 days. Exclusions: exams within 3 days of purchase, name mismatches between candidate and payer, and free or expired products. Prefer a swap? Take two equal-value exam products free, updates intact.

                                                      No formal prerequisites; recommended: hands-on experience with Microsoft Project 2013 and basic project management knowledge Before paying any registration fee, verify the current criteria on the official exam page — official 74-343 exam page — since vendors do revise their rules.

                                                      The official fee is $165 USD (may vary by region), with 700 / 1000 required to pass. Both numbers matter more together: the fee is per attempt, so every retake costs the full amount again. Drilling the 110 practice questions from DumpsActual until you're comfortably past the mark is the fiscally sound approach.

                                                      Yes — the free demo gives you several real questions and answers from the set, so you can see whether it interests you and helps you before spending anything. Once you buy, updates are free for 365 days — new versions are mailed to you automatically — and an expired update period renews at 50% off.

                                                      Microsoft Managing Projects with Microsoft Project 2013 Sample Questions:

                                                      Question #1

                                                      You are a project manager for a software development company that uses Project Professional 2013.
                                                      For managing projects, your company has its own specialized processes, all of which you are familiar with, except for the reporting processes. Additionally, your company's status reports of project progress are based on Work and Cumulative Work.
                                                      Thirty minutes before a meeting is scheduled to begin, the president of your company asks you to present the status report at the meeting.
                                                      You need the report to show all project tasks, resources assigned, and their respective Work and Cumulative Work on a monthly basis.
                                                      What should you do?

                                                      • A. Select the Task Usage view that has all project tasks and resources assigned. Right- click the Details table, selecting Work and Cumulative Work. Adjust the timescale by zooming in or out to fit the monthly basis.
                                                      • B. Select the Gantt Chart view that has all project tasks and resources assigned. Right- click on the Gantt chart, selecting Work and Cumulative Work. Adjust the timescale by zooming in or out to fit the monthly basis.
                                                      • C. Select the Gantt Chart view that has all project tasks and resources assigned. Click Add New Column to add Work and Cumulative Work. Go to the Gantt chart and adjust the timescale by zooming in or out to fit the monthly basis.
                                                      • D. Select the Network Diagram View. Choose Format Box Styles and add Cumulative Work to the Critical Task Box style.
                                                      Reveal Solution  Discussion  0

                                                      Correct Answer: A  🗳️

                                                      Question #2

                                                      You use Project Professional 2013 to manage a project for your organization.
                                                      You are tracking work in a project which contains a baseline and resource assignments.
                                                      You want to view the work variance for a specific resource for a specific task.
                                                      You need to choose a view that will show this information.
                                                      What should you do?

                                                      • A. View the Resource Sheet view and insert the Work Variance field.
                                                      • B. View the Task Usage view and insert the Work Variance column on the left side of the view.
                                                      • C. View the Gantt chart in split view with Task form formatted to show Work Details.
                                                      • D. View the Resource Sheet that shows the Work table.
                                                      Reveal Solution  Discussion  0

                                                      Correct Answer: B  🗳️

                                                      Question #3

                                                      You are a project manager who uses Project Standard 2013.
                                                      You are creating a preliminary project schedule and are estimating the number of resources required prior to finalizing the schedule. You do not have named resources to complete the tasks, but you know the resource roles that are necessary. One of the roles needed is architect.
                                                      You need to estimate how many architect hours are required to complete the work.
                                                      What should you do?

                                                      • A. Add a Material Resource named architect.
                                                      • B. Add a Budget Resource named architect.
                                                      • C. Add a Work Resource named architect,
                                                      • D. Add a Cost Resource named architect.
                                                      Reveal Solution  Discussion  0

                                                      Correct Answer: C  🗳️

                                                      Question #4

                                                      You manage a project by using Project Professional 2013.
                                                      The Indicators column in the Gantt Chart view shows that there are overallocated resources for a task. A resource is assigned to multiple tasks at 100% on a specific day, totaling 2.5 hours of work for the day. The resource has availability of 8 hours for the day.
                                                      You need to solve this problem.
                                                      What should you add to the task?

                                                      • A. More work
                                                      • B. A Finish to Finish relationship
                                                      • C. A Finish to Start relationship
                                                      • D. A deadline
                                                      Reveal Solution  Discussion  0

                                                      Correct Answer: C  🗳️

                                                      Question #5

                                                      DRAG DROP
                                                      You are an independent project manager who uses Project Professional 2013 and wants to extend the standard functionalities of it.
                                                      You need to find and install an app from the Office Store.
                                                      Which four actions should you perform in sequence? (To answer, move the appropriate four actions from the list of actions to the answer area and arrange them in the correct order.)

                                                      Reveal Solution  Discussion  0

                                                      Correct Answer:


                                                      Explanation:
                                                      Box 1: Access the Office Store and log in by using a valid account.
                                                      Box 2: Search for a specific app.
                                                      Box 3: Download and save the app file on your local computer.
                                                      Box 4: Execute the Installation App file to install.
                                                      Note:
                                                      * The new Office Store provides Apps for Office that extend the functionality of Project to solve unique problems to meet your needs and the needs of your business.
                                                      * How do I add an app to Project Pro for Office 365 or Project Professional 2013?
                                                      Open Project. On the Ribbon, click PROJECT, then click Apps for Office.

                                                      All apps for Project associated with your account will show up. If you need to acquire new Apps from the Microsoft Office Store, click the Find more apps in the Office Store link and follow the instructions on the screen.

                                                      Viewing page 1 out of 22 pages.
                                                      Viewing questions 1-5 out of 110 questions.

                                                      5%

                                                      860 Customer ReviewsCustomers Feedback (* Some similar or old comments have been hidden.)

                                                      Took 74-343 exam today and passed it. 74-343 dump still valid! though there are few incorrect answers and some missing questions. Enough to pass anyway!

                                                      Molly

                                                      Molly     4 star  

                                                      Good, I have pass 74-343 exam, and I really appreciate my friends recommend the DumpsActual to me, and thank you!

                                                      Morton

                                                      Morton     4 star  

                                                      DumpsActual is the best site for dumps. Previously I studied for some other exam and scored well. Now i passed my 74-343 exam with 92% marks.

                                                      Norton

                                                      Norton     5 star  

                                                      Wonderful 74-343 dump. So happy to passed my exam easily, it is agreat website.

                                                      Tobey

                                                      Tobey     5 star  

                                                      Both of the exams are the latest 74-343 dump.

                                                      Winni

                                                      Winni     4 star  

                                                      Passed today with this 74-343 practice test. I didn't studied the books at all, only learned this 74-343 practice test. And i passed with 98% scores. I am glad with this result!

                                                      Sebastian

                                                      Sebastian     4 star  

                                                      Bought the 74-343 dumps they were cheaper than I thought. Also, they helped me in passing the exam.

                                                      Quentin

                                                      Quentin     4.5 star  

                                                      I thought 74-343 exam is very difficult and I never thought that I would pass this 74-343 exam ever.

                                                      Kimberley

                                                      Kimberley     4.5 star  

                                                      Yes, it is valid. And after you studied with the 74-343 exam questions, when you attended the exam, you would feel everything is sheduled, it is just you to show up and play. I passed the exam smoothly with ease.

                                                      Quintion

                                                      Quintion     5 star  

                                                      I really needed some dumps like 74-343 exam dumps to help me. I will recommend it to everyone. Good work DumpsActual.

                                                      King

                                                      King     4 star  

                                                      DumpsActual dump 74-343 valid yesterday. 96%

                                                      Luther

                                                      Luther     4 star  

                                                      Passed 74-343 exam two weeks ago! 100% from these 74-343 practice dumps, but you have to study more carefully to make sure you pass at the first time.

                                                      Brook

                                                      Brook     5 star  

                                                      With 74-343 you will experience an evolution of products coupled with the experience and qualities of expertise.

                                                      Byron

                                                      Byron     4.5 star  

                                                      LEAVE A REPLY

                                                      Your email address will not be published. Required fields are marked *

                                                      QUALITY AND VALUE

                                                      DumpsActual Practice Exams are written to the highest standards of technical accuracy, using only certified subject matter experts and published authors for development - no all study materials.

                                                      EASY TO PASS

                                                      If you prepare for the exams using our DumpsActual testing engine, It is easy to succeed for all certifications in the first attempt. You don't have to deal with all dumps or any free torrent / rapidshare all stuff.

                                                      TESTED AND APPROVED

                                                      We are committed to the process of vendor and third party approvals. We believe professionals and executives alike deserve the confidence of quality coverage these authorizations provide.

                                                      TRY BEFORE BUY

                                                      DumpsActual offers free demo of each product. You can check out the interface, question quality and usability of our practice exams before you decide to buy.